Old 02-07-2014
You can make a crontab running every day, and then test if its the second day on mont, like this:
Code:
20 0 * * * [[ $(date +%d) -eq 2 ]] && Your script here

It will then only run on date 2 in the month at 12:20 am
 

10 More Discussions You Might Find Interesting

1. UNIX for Advanced & Expert Users

Documentation and books on Autosys Job Control Tool from Autosys

My project uses Autosys. I am new to this product and I don't know where to start from. Q1. Please provide me the link where I can get Autosys documentation Q2. Please refer a good book on Autosys. (Beginner/Intermediate Level) (0 Replies)
Discussion started by: gram77
0 Replies

2. Shell Programming and Scripting

Job Scheduling

I am working on UNIX AIX system, with Oracle OS. We are not supposed to use any tools to schedule our unix shell scripts. Basically we have to make use of Oracle tables and Shell scripts to manage dependencies, restartability, scheduling, parallelizing,etc. If anyone has worked/ is working... (4 Replies)
Discussion started by: singhabhijit
4 Replies

3. Shell Programming and Scripting

Job Scheduling Issue

Hi Guys, I am new to Unix, Please tell me how to schedule a job to be executed on saturday,sunday and on friday night 8:00 PM onwards. and also how to change the password of oracle user every year through unix? Please help me to resolve this issue... Regards, Mahesh Raghunandanan (1 Reply)
Discussion started by: mraghunandanan
1 Replies

4. UNIX for Advanced & Expert Users

Autosys job scheduling

Hi, I want to schedule a job through Autosys (in Linux server) to run on 1st day of every 3rd month(gap of 90 days). Please someone help me to achive my above requirement Example: Run the sample.sh on 01-Jan-2009, 01-Apr-2009, 01-Jul-2009, 01-Oct-2009. Thanks in advance (4 Replies)
Discussion started by: apsprabhu
4 Replies

5. UNIX and Linux Applications

Job Scheduling (Autosys)

Hello! I will be working with Autosys and I am looking for individuals that have knowledge of this UNIX application. Thank-you! (3 Replies)
Discussion started by: preshe79
3 Replies

6. Shell Programming and Scripting

autosys job configuration for job failure.

We need to configure autosys that when a job fails continously for 3 times, we need to call another job. Is this possible in Autosys, or can anyone advice on the alternative. (2 Replies)
Discussion started by: sangea
2 Replies

7. UNIX for Advanced & Expert Users

Issue while killing the process using autosys job

Hi, I have one autosys job that will retrieve the proccess id's and will kill those processess as follows, pid=`/usr/ucb/ps -auwwxx | grep MAIN |nawk '{print $2}'` kill -9 pid but after executing this particular job, its status is showing as TE(terminated) and the kill process is... (3 Replies)
Discussion started by: Kattoor
3 Replies

8. Shell Programming and Scripting

Autosys job scheduling on specific day

Below is the requirement i am trying to do using auto sysjob. I need to create a JOB or script which will do the below things for me I have a box and there corresponding jobs as below BOX_1 JOB_1 JOB_2 BOX_2--- SU(JOB_2), this will run only on completion (Success) of JOB_2 ... (2 Replies)
Discussion started by: j_panky
2 Replies

9. Shell Programming and Scripting

Job Scheduling

Hi All, I am new to unix and i have a task in front of me. The code part is "android update sdk" . I need to crontab this process. Hence i have written a script that runs the above command and sends a mail once the update is done. The problem with the automation is the installer asks for a... (5 Replies)
Discussion started by: Kashyap
5 Replies

10. UNIX for Advanced & Expert Users

Autosys Job: Job did not start

I have submitted an autosys job and force start it. Autosys hit the job 4 times to restart but it did not start and finally I terminate the job. Any idea why the job did not start. Below is the code I executed. 1214 missun0ap /export/home/bzn97r/develop/dswi/jil$ sendevent -E FORCE_STARTJOB... (0 Replies)
Discussion started by: jnrohit2k
0 Replies
widget_calendar(n)					    widget::calendar Megawidget 					widget_calendar(n)

__________________________________________________________________________________________________________________________________________________

NAME
widget_calendar - widget::calendar Megawidget SYNOPSIS
package require Tcl 8.4 package require Tk 8.4 package require widget ?3.0? widget::calendar pathname ?options? _________________________________________________________________ DESCRIPTION
This package provides a calendar megawidget (snidget). widget::calendar pathname ?options? WIDGET OPTIONS
-command A script to evaluate when a date was selected. -dateformat The format of the date that is returned. Default: %m/%d/%Y. -firstday Set first day the week, Either sunday or monday. It defaults to monday. -font Select the font used in the widget. It defaults to Helvetica 9. -highlightcolor Selects the background color for the day that has been selected. Default: #FFCC00 -language Specify language of the calendar contents. The language is specified by abbreviations of the languge, for example: en - english, de - german ... It defaults to en. Supported languages: en, de, fr, it, es, pt, ru, sv, zh, fi -shadecolor Selects the color of the parts that have a shaded background. Default: #888888 -showpast Specify if the past shall be shown. It is a boolean value and defaults to 1. -textvariable Specifies the name of a variable whose value is linked to the entry widget's contents. Whenever the variable changes value, the widget's contents are updated, and vice versa. WIDGET COMMAND
pathname get ?what? Returns a part of the selected date or 'all'. The argument what selects the part. Valid values for what are: day, month, year and all. 'all' is the default and returns the complete date in the format given with -dateformat. DEFAULT BINDINGS
On creation of the calendar widget the following bindings are installed. o Up - Move to week before current date o Down - Move to week after current date o Left - Move to day before current date o Right - Move to day after current date o Control-Left - Move to month before current date o Control-Right - Move to month after current date o Control-Up - Move to year before current date o Control-Down - Move to year after current date EXAMPLE
package require widget::calendar ; # or widget::all set t [widget::calendar .t] pack $t -fill x -expand 1 KEYWORDS
megawidget, snit, widget widget 0.93 widget_calendar(n)
All times are GMT -4. The time now is 05:22 AM.
Unix & Linux Forums Content Copyright 1993-2022. All Rights Reserved.
Privacy Policy